Mep Work Progress Report: Sample Portable

MEP works are highly interdependent. Highlight if electrical work is delayed due to HVAC ducting issues. Color Code:

| Discipline | Planned Progress (%) | Actual Progress (%) | Status | Remarks | | :--- | :---: | :---: | :---: | :--- | | | 45% | 43% | 🟡 Slight Delay | Ductwork installation ongoing; lag due to ceiling obstruction. | | Electrical | 50% | 50% | 🟢 On Schedule | Cable pulling for floors 1-3 completed. | | Plumbing & Fire Fighting | 38% | 35% | 🔴 Delayed | Delay in approved shop drawings for pump room. | | Fire Alarm | 25% | 25% | 🟢 On Schedule | Device mounting on Level 4 in progress. | mep work progress report sample

Specific tasks finalized during this period (e.g., "Riser piping for plumbing completed"). Ongoing Work: MEP works are highly interdependent